Client: Emirates General Petroleum Corporation (Emarat)
Project Name:
- Conversion of Tanks TK-2 & Tk-3 with associated piping.
- Above Ground Floating Fuel Storage Tank Maintenance (Tank 7)
- Radar Tank Gauging System.
- Replacement of Sea water intake pump strainers with diving team.
- Leak Detection and Repair of Underground Diesel line at SAQR Port.
- Supply and Installation of Floating Roof for Above Ground Fuel Storage Tank.
Year of Construction: 2010-2020
Type of contract: Main Contract
System: Tank Roof replacement and Floating roof Installation
- Leak Detection of Underground Pipeline
- Radar Tank gauging system
- Tank Hydro testing with seawater
- Sea water intake Strainer Replacement
- Tank painting – Full Internal & External for 3
Tanks Mechanical: Replace full roof of 40 meter diameter fuel storage tank. Replace damaged shell walls, Install floating roof for 2 storage tanks. Piping works in tank farm and pump station. Replacement of 36-meter dia tank annular plate, Repair works on 25-meter dia, 15-meter height fuel storage tank including floating deck. Under Ground Diesel line leak detection and repair works from berth to terminal.
Structural: Tank platforms and staircase, roof supports, valve operation platforms. Painting internal and external of 3 storage tanks including internal roof.
Civil: Excavation and office modification works, Pipe Civil Foundation, Valve Pit Construction.
Electrical & Instrumentation: Radar Tank Gauging system relocation with underground cabling Power, communication and optical fiber cabling network up gradation.
Tank Hydro test: Carry out hydro test using sea water for 3 no’s of big fuel storage tanks with all authority approvals.